Sovereign AI Cloud Design and Run-Cost Assessment

A design and a costed plan for a private cloud you own, standing on your site or in a data centre you nominate. Documented in the

Record
System AudiTraxLabs
Published on auditraxlabs.com

Sovereign AI Cloud Design and Run-Cost Assessment before you commit capital.

When AI workloads have to run on infrastructure you own or control, public cloud pricing models break. We assess the site, the power, the cooling, the network fabric, the model footprint and the three year run-cost before you sign a hardware contract.

What a private sovereign AI cloud is actually made of

Five layers, one boundary, and a single controlled channel out of it. The assessment establishes what you already have at each layer and what has to be designed.

Figure 1 · Sovereign AI cloud reference architecture

Sovereign boundary and facility constraints

Systems you own and operate

The design is written so it can be tendered. Nothing in it depends on a single vendor, and the layer boundaries are the same ones your procurement team will contract against.

Six questions, answered with measurements rather than assurances

The workloads you actually intend to run

Training, fine tuning and inference behave nothing alike, and sizing for the wrong one is the most expensive mistake in this whole exercise. We profile the real demand curve rather than the peak somebody quoted.

The residency and regulatory boundary

Which rules actually bind you, what they require of data at rest, in transit and in the model, and where your current estate already crosses the line without anyone noticing.

The site, power and cooling headroom

Accelerator racks draw many times what a typical enterprise rack does. We walk the floor and establish whether the building can carry the design, or what has to change first, before anything is ordered.

The hardware and network design

A sized, vendor-neutral bill of materials with the network fabric that actually feeds it. Written so you can put it out to tender rather than back to the vendor who suggested it.

The three year run cost

Hardware amortisation, power, cooling, network, licences, spares and the operations team, modelled year by year and compared honestly against staying on public cloud.

Efficiency, measured rather than claimed

Cost per million tokens and energy per result, measured on a representative workload and stated against published standards so a third party can reproduce the figure.

Where the money actually goes once the hardware is paid for

The quote you were shown covers the first block below. The assessment covers all seven, then divides the total by the work the system does.

Figure 2 · Three year cost stack and efficiency derivation

What we look for when we walk the floor

Three minutes inside a site assessment: rack density, cooling method, power headroom, and the constraints that decide the design before anything is ordered.

Walking the floor

3:44 · Site assessment video

What crosses the line, and what never does

The design allows exactly one channel out of the sovereign boundary, and it carries telemetry only. This is the drawing that settles the argument with a regulator.

Figure 3 · Traffic across the sovereign boundary

One product, three tiers, chosen by how hard the number has to be

Every tier answers the same two questions: Will your AI and data architecture survive your regulator, and what does it actually cost to run.

Standard

A defensible first answer for a board that has been asked the question.

$18,500

4 weeks · Remote, document led

Extended

Adds the measured run-cost and energy figures. This is where the number becomes yours.

$34,000

6 weeks · Includes a site visit

Regulated

For an organisation that has to hand the result to a regulator, an auditor or acquirer.

$52,000

8 weeks · Site visit and benchmark run

The awkward ones, answered first

Will you tell us not to build it?

Sometimes, and we have. If the workload is small, bursty or short-lived, public cloud usually wins on cost and we will show you the crossover point rather than talk around it.

Are you going to recommend a build you then get paid for?

A firm connected to us can execute builds, and that is disclosed on page one of every report. The assessor takes no part in the build and no part of their pay depends on the recommendation. The design is written so any competent integrator can deliver it.

Our vendor already gave us a design. Why pay for another one?

Bring it. A large part of what we do is testing a vendor design against the workload and the building it has to live in. If it holds up we will say so, which is worth knowing before you sign a multi-year commitment.

Can the operations centre really sit outside the boundary?

Only if the channel carries telemetry and no customer data, and only if your regulator accepts that split. We establish which of those is true for you rather than assuming, and design the boundary accordingly.

Tell us the workload and the building. We will tell you whether it can carry it

Thirty minutes is usually enough to scope it, and we will be honest if public cloud is the better answer.

Sovereign AI Cloud Design and Run-Cost

4 to 6 weeks · Fixed fee · Full bill of materials